Title
Approve the following with Central Asphalt for NRCS Evergreen/Iowa/Patricia Sites:
1. Authorize Mayor to execute Contract Amendment No. 3 for a net decrease in contract in the amount of $35,916.60 and allow an additional 15 calendar days
2. Approve Contractor's Progress Estimate #7 (Final) in the amount of $6,428.07
3. Accept Certificate of Substantial Completion
4. Accept Close Out Documents (Surety Release/ Consent to Final Payment, Contractor's Affidavit for Release of Liens, Contractor's Affidavit for Payment of Debts and Claims)