Title: Approve the following with Central Asphalt for NRCS Evergreen/Iowa/Patricia Sites: 1. Authorize Mayor to execute Contract Amendment No. 3 for a net decrease in contract in the amount of $35,916.60 and allow an additional 15 calendar days 2. Approve Contractor's Progress Estimate #7 (Final) in the amount of $6,428.07 3. Accept Certificate of Substantial Completion 4. Accept Close Out Documents (Surety Release/ Consent to Final Payment, Contractor's Affidavit for Release of Liens, Contractor's Affidavit for Payment of Debts and Claims)
Attachments: 1. CA #3- Final Pay App #7 Evergreen-Iowa-Patricia
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Approve the following with Central Asphalt for NRCS Evergreen/Iowa/Patricia Sites:

1. Authorize Mayor to execute Contract Amendment No. 3 for a net decrease in contract in the amount of $35,916.60 and allow an additional 15 calendar days

2. Approve Contractor's Progress Estimate #7 (Final) in the amount of $6,428.07

3. Accept Certificate of Substantial Completion

4. Accept Close Out Documents (Surety Release/ Consent to Final Payment, Contractor's Affidavit for Release of Liens, Contractor's Affidavit for Payment of Debts and Claims)