Title: Approve the following with Fordice Construction Company for NRCS Sportsforce Site: 1. Authorize Mayor to execute Contract Amendment No. 2 for a net increase in contract in the amount of $13,608.83 2. Approve Contractor's Progress Estimate #7 (Final) in the amount of $75,243.84 3. Accept Certificate of Substantial Completion 4. Accept Close Out Documents (Surety Release/ Consent to Final Payment, Contractor's Affidavit for Release of Liens, Contractor's Affidavit for Payment of Debts and Claims)
Attachments: 1. CA #2-Final Pay App #7 Sportsforce
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Approve the following with Fordice Construction Company for NRCS Sportsforce Site:

1. Authorize Mayor to execute Contract Amendment No. 2 for a net increase in contract in the amount of $13,608.83

2. Approve Contractor's Progress Estimate #7 (Final) in the amount of $75,243.84

3. Accept Certificate of Substantial Completion

4. Accept Close Out Documents (Surety Release/ Consent to Final Payment, Contractor's Affidavit for Release of Liens, Contractor's Affidavit for Payment of Debts and Claims)