File #: ID-25-0048    Version: 1 Name:
Type: Action Item Status: Passed
File created: 1/9/2025 In control: Board of Mayor and Aldermen
On agenda: 1/10/2025 Final action: 1/10/2025
Title: Approve the following with Central Asphalt, Inc. for NRCS Iowa Sites 1 & 2: 1. Authorize Mayor execute Contract Amendment No. 1 for a net reduction of the contract amount of $12,492.85 and allow an additional 20 calendar days 2. Approve Contractor's Progress Estimate #4 (Final) in the amount of $14,666.06 3. Accept Certificate of Substantial Completion 4. Accept Close Out Documents (Contractor's Affidavit of Payment of Debts and Claims, Contractor's Affidavit of Release of Liens, Consent of Surety to Final Payment)
Attachments: 1. CA #1-Final Pay App #4 Iowa Sites 1&2

Title

Approve the following with Central Asphalt, Inc. for NRCS Iowa Sites 1 & 2:

1. Authorize Mayor execute Contract Amendment No. 1 for a net reduction of the contract amount of $12,492.85 and allow an additional 20 calendar days

2. Approve Contractor's Progress Estimate #4 (Final) in the amount of $14,666.06

3. Accept Certificate of Substantial Completion

4. Accept Close Out Documents (Contractor's Affidavit of Payment of Debts and Claims, Contractor's Affidavit of Release of Liens, Consent of Surety to Final Payment)