Title:
|
Approve the following with Southeastern Pipeline & Environmental Services for 8" Gas Line Extension - Wisconsin Blvd to Gay Blvd Project:
1. Approve Pay Application #3 (Final) in the amount of $25,000.00
2. Accept Final Completion Certificate