File #: ID-26-0336    Version: 1 Name:
Type: Action Item Status: Agenda Ready
File created: 3/19/2026 In control: Board of Mayor and Aldermen
On agenda: 3/25/2026 Final action:
Title: Approve the following with Southeastern Pipeline & Environmental Services for 8" Gas Line Extension - Wisconsin Blvd to Gay Blvd Project: 1. Approve Pay Application #3 (Final) in the amount of $25,000.00 2. Accept Final Completion Certificate 3. Accept Close Out Documents (Final Release of Debts and Liens, Consent of Surety to Final Payment)
Attachments: 1. Southeastern Pipeline & Environmental Services Final Documents

Title

Approve the following with Southeastern Pipeline & Environmental Services for 8" Gas Line Extension - Wisconsin Blvd to Gay Blvd Project:

1. Approve Pay Application #3 (Final) in the amount of $25,000.00

2. Accept Final Completion Certificate

3. Accept Close Out Documents (Final Release of Debts and Liens, Consent of Surety to Final Payment)